1. Perform the necessary excavation. Always remove the topsoil.

2. Place the borders. These should be 2 cm above the level of the top of the sheet.

3. Dig the foundations. Work in max. layers of 20 cm and compact with a vibrating plate.

4. Install the levelling layer in fine gravel, compact and level.

5. Install the ECCOgravel® with overlapping geotextile. Cut with a cutting disc. Then, lay sheets in halfbrick bond.

6. Lay the gravel. First the gravel then moving loads. Level with a shovel, brush, rake and tamp. Do not compact the decorative gravel. Leave the gravel ± 2 cm above the sheets. The gravel will sink slightly as a result of natural compaction. Eventually, there should be just enough gravel to hide the ECCOgravel® sheets.

7. Inspect and level a few weeks after initial use. Add gravel where necessary. Sinking will no longer occur.

Visit our Landscape Projects & Case Studies

Latest News

CED Stone Support Local Community with John Newton Plaque in Purfleet

Saturday saw the 'eventual' unveiling of a plaque celebrating John...posted 23 Jul, 2024